The Department of Environmental Quality has approved a plan intended to preserve water quality during construction of the Mountain Valley Pipeline. The agency says the erosion, sediment and storm water control plans for the pipeline will protect water quality in all areas of Virginia. Until now, pipeline work has been limited to cutting trees along its path and leaving them where they fell. MVP is now permitted to begin full-scale construction.

From Virginia DEQ: RICHMOND, VA. – The Virginia Department of Environmental Quality has approved the Erosion and Sediment Control, Stormwater Management, and Karst Protection Plans for the Mountain Valley Pipeline effective today, March 26, 2018. These detailed site plans specify engineering designs that will protect water quality in all areas of Virginia, including karst, during and after construction of the pipeline project.

DEQ began its plan review in March 2016, which continued with a more thorough review beginning in June 2017 by EEE, an independent consulting firm. Today’s approval authorizes MVP to begin land disturbing activities in Virginia consistent with these plans. No changes to the plans may be made without obtaining prior approval from DEQ. The basis for the design specifications for the plans are contained in Virginia’s erosion and sediment control and stormwater management regulations.

“Protecting water quality and water supplies is our greatest concern,” said David K. Paylor, DEQ Director. “We required MVP to submit detailed plans for every foot of land disturbance, and we carefully reviewed all aspects of these plans.”

Draft plans were posted for the public for input in September 2017, and the final plans are now available to view at https://www.mountainvalleypipeline.info/current-news.

In response to public interest, DEQ has sent a report to the State Water Control Board (Board) detailing the approval of the Erosion and Sediment Control, Stormwater Management, and Karst Protection Plans, which are required by regulation to protect the Commonwealth’s waters.

“DEQ’s enhanced review, along with our new stop-work authority, gives the agency a variety of tools to protect water quality across the range of pipeline activities and ensure developers comply with Virginia’s rigorous regulatory requirements,” added Paylor.